This AddIn provides functionality to Import and Export MS Project .mpp files to and from Aras Innovator Projects. v0.3 supports 64-bit applications Project 2019 and is tested with Innovator v12SP3 and Project v12.0R1. Different AddIns will be required for 32-bit versions such as Project 2010 and earlier.
Clarify that activities with a roll up predecessor need to be updated so the predecessor is not a roll up task.
Otherwise it seems that those predecessors should be removed, and that changes the project schedule.
Clarify that activities with a roll up predecessor need to be updated so the predecessor is not a roll up task. Otherwise it seems that those predecessors should be removed, and that changes the project schedule.