  1. If wall has fire/insulation as wall type instead of LB/LBS, than also we need to place cee headers & decks considering those lines simlarly to LB lines. (This is needed as Fire & Insulation wall type lines are also load bearing wall lines similar to LB lines which may have cee headers if they run along the parallel direction of LB walls or perpendicular to roof slope).

  2. If there is a LB wall & if there are NLB walls there after this LB wall, with no other LB walls in alignment, then we need to place the Cee headers connecting LB end to NLB wall & thereafter again from NLB to NLB or NLB wall line to LB as needed.

  3. Even W-beam which is placed instead of LB wall line also, can be considered as a LB wall for deck lapping.