Open rebekkabry opened 2 months ago
Attendees: Ron, Reza, Rebekka, Binaya, Ambarish
TPW Roles: Reza - planning Andre - ops/ specifications and status updates
Currently vs Proposed by Stakeholders
Milling is first. Pavement is last. Is there other work in between.
MIll and Over separate, not as the dependent child of the work order.
Attendees:
Goal: split the team into 2: milling and paving team
Current: the way we have the two crews we cant
Milling can do more than paving, currenting cant completel milling becuae have to wait for overlay.
Can you not change the status the parent without the child being complete? we can 4qa the child, but we cant get credit for the overall work order until the pavig is done. doesnt show up on completed lane miles report.
could we run a report on the milling children? as an option. ---the concern: one report that would show them stand alone.
paving and milling children of the parent work order = not want they wont.
if we can report indentpendly doesnt need to change.
@GaneshKamarapu - can we discuss the efforts on this? and how much it may align with this request #14546
[ ] Service Plans:
SP24-SLCT1
SP24-SLCT2
[ ] Workgroup
Overlay
[ ] Separate by Work Order Children
Milling: -MILL
Pavement: -OVL
[ ] Status
any 4
[ ] Metrics and Parimeters
by week; (daily and previous 7 days possible) able to run daily but see the count of the last 7 days
Count of completed WO by (MILL, OVL, PROJECT WO)
Count of miles by (MILL, OVL, PROJECT WO)
@GaneshKamarapu we can add to the upoming August 7th sprint.
BUILD followup Pg 1: Total Graph - with data (current phase) Pg 2: Mill ONLY Graph with data Pg 3: OVRLAY ONLY Graph with data * may be best to use the WorkGroup as the Work Orders do not specify the OVL Children Work Orders
@GaneshKamarapu Lets put this on hold per Ron pending Andre's return and rescoping.
Background
Pavement has requested the Overlay and Milling hierarchy be removed to allow for independent work order handling within the Pavement Service Plan
Reasons for Requests: Overlay and Milling are dependant upon the status of the other workorder before being able to go out and complete the work. They will like to be able to complete the work, regardless if the Parent has been completed. We need to ensure the Parent does not have any required conditions needed for the Child, which is why currently dependant.
Desired Completion: In preparation for FY25 Service Plan Upload
Stakeholders to Sign Off and Approve Before Any Changes are Made
Concerns to Investigate
Scoping Plan
CURRENT
PROPOSED