Open descalona2023 opened 11 months ago
I'm facing similar problem here. I updated the hours in ms project and sync to redmine, it works fine. When I load back the information, the hours became wrong, it was multiplied by 12.5 in days. So, 16 hrs loaded as 200 days... If I change the project options to use hours by default, the loaded duration became multiplied by 100 (see the image below). There is some setup I'm missing? I'm using Redmine version 5.1.3.stable and
Hi @pesseba, what's the language in your PC, and what's the languange in your Redmine account(you can see it in the profile page)?
Hi @conveniencable, I'm running in pt-BR
. The decimal uses ,
insted .
Example:
The MS Project version is:
Microsoft® Project 2019 MSO (Versão 2407 Build 16.0.17830.20166) 64 bits
pt-BR
Thank you, I find the problem now, both this plugin and redmine plugin need to be fixed. Just I am sorry I don't have time currently, I will fixed it this week.
Hi @pesseba, please update this redmine plugin to V1.0.17 (the latest currently), and also update the MS Project plugin to V1.0.23
The update worked @conveniencable. Thanks!
When loading my information from project to redmine, it is imported by multiplying the work hours by 60, so it's not the correct information, as you can see in the following images:
How can I make this import without these durations changing?