Open brianfunk opened 8 years ago
We intend to work in an agile way, and therefore the "due date" of the development prototype is not intended to convey that the product will be finished, but rather that some number of development user stories will be delivered in each sprint, beginning with Sprint 2.
Question/Comment on e-QIP Prototype RFQ
Name and affiliation
Brian Funk - NCI, Inc - Agile BPA Manager
Section of RFQ documents
PWS. Section 6.6.3 List of Deliverables “In-progress development prototype, accessible on the web via staging server / development server”
Question/Comment
The development prototype is due at the end of Sprint 2. Is it expected that this initial prototype will have all functionality described in the PWS at that time? Or will the features included in this initial prototype be based on prioritization from the Product Owner working with the Product Lead and development team?