Finish clean room #1

Open wetstein opened 6 years ago

wetstein commented 6 years ago

Complete the building of the clean room facility for ANNIE Phase II staging and PMT mounting.

etiras commented 6 years ago

The cleanroom drawings are done. Jim will order the materials on Mon/Tues (Oct 15-16).

etiras commented 6 years ago

The materials were ordered and the expected delivery date is December 7th.