Before our next test we'll need to do some hefty manual testing for a few reasons
We're potentially rewriting the complex sequencing logic
We need to improve our testing game before we start using liquid oxygen
We've caught minor issues during testing days before. From now on we can't afford to risk small bugs or testing bug fixes during a live test and we also really don't want a test day cut short over a minor issue with a 2 line fix
I'm thinking we get a few people together for a solid half day and just mash buttons and see if we can break things
We can fix bugs during this low stakes manual testing day, but once we've approved a revision of the code, we will feature freeze before the quarry testing day
We also need to check that all of the electronics kit is present - we've just potentially lost our raspberry pi, if we only found this out the day before a test we'd be out of luck
Before our next test we'll need to do some hefty manual testing for a few reasons
I'm thinking we get a few people together for a solid half day and just mash buttons and see if we can break things
We can fix bugs during this low stakes manual testing day, but once we've approved a revision of the code, we will feature freeze before the quarry testing day