Open ABurton22 opened 1 year ago
Aaron + Jeff to work on an open architecture comment period to allow chain communities to provide initial feedback Will present back to coalition on 10/20 Yves (+2), Guillaume (+1), Jesse in milestone 1 review
first weekly update mtg first revision of the architecture document completed Aaron to distribute the arch doc to Yves, Guillaume, Jesse
Doodle in core channel for new weekly review meeting
Milestone sequencing will be adjusted; milestone definitions are the same
Milestone #2 (core) and #8 (branding) in flight
Vote to rebaseline with new V4 schedule EOS: Yes Telos: Yes WAX: Yes UX: Yes
Jeff to implement change control for contract and project status
Call yesterday
Douglas needs info on creating the MSig - will contact participants + Aaron
ENF to transfer funds from earmarked fund to newly created account
Champions: Yves, G, Jesse
Douglas to create MSig (with Aaron support)
ENF to transfer funds from earmarked fund to newly created account
Contract signed
Contract very close to be signed now, all components agreed.
Meeting for project status reports and organization to be organized once contract is signed.
Proposal Douglas: Telos Core Developers to verify additional resources to support Antelope Project Coordination and follow up next to ENF (Jeff, Adam)
Guillaume offered additional resources for technical reviews.
WAX, Kersten to approach Lukas
Project contract has not been signed
Contract draft is being worked on by Jeff. ENF signs on behalf of Antelope. Draft to be distributed this week, signature expected next weeks.
Start of project expected 4-6 weeks latest.
Technical perspective:
Marketing perspective:
Contract sent to Greymass; under review
Currently, the Antelope entity doesn't exist. Will coalition transfer the funds before the contract execution and EOS will own the liability of payment? Use an account with EOS control and MSigs to approve milestones
Aaron and Yves to create a proposal on the new account
Denis to reserve antelope.wg (Yves will track down)