cptResourceDemand - use Resume instead of subtracting actuals #353

Closed AronGahagan closed 10 months ago

AronGahagan commented 10 months ago

Problem:

Subtracting timescaled actuals from timescaled work can be inaccurate in certain situations.

Solution:

Use Resume date instead of Start for in-progress tasks instead.

Todo:

AronGahagan commented 10 months ago

it already does this, you dope