20240510_ Patrick, Gino, Hank, Tom, Richard, Jacob, Bill

  1. Schedule review ISTA 3A-表定10天,5/10出貨 有沒必要加測ISTA 1A?

  2. Actions once signed off DVT Material readiness-Belle DFM-Claire下周一NPI提出 Line efficiency balance-對外Claire F,

  3. 一天產能200的話,要20個人,代工廠10人是不夠的。 Owner: Richard,如何做200pcs? 加$?

4. 人,機,料

  1. 代工廠5/13提供SOP

  2. Shopfloor-要每週review

  3. 螺絲規格確認,5/13要收到客戶確認

  4. Camera module交期來不及 目前廠商回覆交期為: 6/14-1K, 6/28-1K

  5. 人力配置必須規劃

  6. Fixture何時可以到-要注意Station 1.2

BelleShen commented 1 month ago

20240513_With Cheney Patrick, Gino, Tom, Belle

  1. Cycle time & line balance & estimated UPH/UPD 需要增設多少治具
  2. PVT & MP on schedule or not

Cheney提醒

Schedule,料況 overview,有何改善計畫optimization。

BelleShen commented 1 month ago
  1. 專案人員配置 Tom, Claire F, Sharon, Albert Tu (background)
  2. 內部時程安排 Build plan
  3. SOW-與Mike討論狀況 5天達成與否? UPD要30個人, 當初報NRE的base是50, e-mail找出來, 要做幾個工作日。

不要談spot buy amount

BelleShen commented 1 month ago

20240515_DVT result review Jon, Kris, Albert, Cheney, Tom, Albert Tu, Claire F, Sharon, Brandt

  1. Inspiren wants to update the fabrication noted for Back PCB Image
  2. Update Main PCBA solder stencil Image
  3. Return all test PCBAs for TS1 and TS2. Image

Mike would like to see the analysis. GT needs to provide a corrective action.

Image Mike doesn't agree to just update the flash image and let GT download it. Image

Image