Closed claris0911 closed 1 year ago
Completed unadjusted use case weight. Can also be found on the drive Calculations.xlsx sheets
no commits
[Day/Month/2023] - (details) 23/9/2023 - Completed unadjusted use case weight
20/9 - 23/9
Completed technical complexity factors. Can also be found on the drive Calculation.xlsx sheets
no commit
[Day/Month/2023] - (details) 23/9/2023 - Completed technical complexity factors
20/9 - 23/9
completed calculation of UCP
UCP = (UUCW + UAW) TCF ECF UCP= (145 + 13) 1.035 0.695 UCP = 113.65 (5s.f.)
No commit
[Day/Month/2023] - (details) 23/09/2023 - Completed calculation of UCP
21/9 - 23/9
Effort Estimation Optimistic Total Hours: 113.65 UCP 15 hours = 1704.75 Total Hours Pessimistic Total Hours: 113.65 UCP 30 hours = 3409.5 Total Hours
Optimistic Total Hours per developer: 1704.75 Total Hours / 5 = 340.95 Hours Pessimistic Total Hours per developer: 3409.5 Total Hours / 5 = 681.9 Hours
Optimistic hours for one developer per week: 340.95 Hours 8 weeks = 42.61875 Hours Pessimistic hours for one developer per week: 681.9 Hours 8 weeks = 85.2375 Hours
Duration Estimation Mean = [Optimistic Duration + (4 Most Likely Duration) +Pessimistic Duration] / 6 Mean = [1704.75 + (4 625.075) + 3409.5]/6 =1269.09167 hours
Standard Deviation = Pessimistic Duration - Optimistic Duration 6 Standard Deviation = [3409.5 - 1704.75]/6 = 284.125
Variance = Standard Deviation2 Variance = 284.1252 * 284.1252 = 80727.0156
Work Done: Completed environmental complexity factors. Can also be found on the drive Calculation.xlsx sheets
Work Done: Completed actor weight. Can also be found on the drive Calculations.xlsx sheets
Work Done: completed calculation of UCP
UCP = (UUCW + UAW) TCF ECF UCP= (145 + 13) 1.035 0.695 UCP = 113.65 (5s.f.)
About:
M1 report project estimation and plan describes the resources required and overall time estimated for the project.
Goals:
produce and calculate correct estimations
produce complexity factors
Success - Completion Details:
[x] software estimation
[x] unadjusted use case weight
[x] unadjusted actor weight
[x] technical complexity factor
[x] environmental complexity factor
[x] use case points calculation
[x] effort estimation
[x] duration estimation
[x] resource estimation
[x] size estimation
[x] gantt chart
[x] wbs
Allocated Time:
4 days
Start date - End Date:
20/9 - 23/9
Person-in-charge:
Task Status:
Priority:
Notes: