CCI-MOC / epics

The Issues within this repo will provide a space for us to track discussions around the creation of our epics. It will allow us to have a single location to track our planning and decisions for epics.
0 stars 0 forks source link

[Epic] Bring up R4-PA-C21 "Research Rack" #53

Closed joachimweyl closed 10 months ago

joachimweyl commented 1 year ago

Motivation

We are working on deprecating our old hardware. Many of the nodes we have are being used by researchers and other projects. The plan is to free up the old nodes so that we can deprecate them. This will start a chain reaction. Once we can move everyone off of a rack or two worth of space we can deprecate those nodes and fill those racks with new nodes, then we can move even more processes into those racks, and so on and so forth.

Completion criteria

New Racks up and running with 2-4 new systems and the rest donated FX2s with 2 z9100 and 1 s3048.

Description

Stand up a new rack that we can move the Researchers to and free up the HIL/BMI nodes. This will allow for a chain reaction of upgrading old nodes.

References

  1. epic

Changelog

2023-06-16: add epic link 2023-08-29: updated Description

joachimweyl commented 1 year ago

we are using R4-PA-C21 for this

joachimweyl commented 1 year ago

PR for node manifest for ESI - Mainn Power testing - Hakan 2-4 modern nodes - Erik Add to ESI - Hakan provides a switch manifest, and Mainn will enroll into the current ESI