Closed lzwsl closed 2 years ago
1) What did you work on this past iteration (2 weeks)?
Worked on user login, user logged in persistence Worked on user authentication with mongodb
2) What were any major issues/challenges you ran into?
Determining how users could be authenticated Getting DB access correctly
3) What do you plan to work on for this coming iteration (2/3 weeks)?
Finalize user login methods as well as determine optimal user state
1) What did you work on this past iteration (2 weeks)?
2) What were any major issues/challenges you ran into?
3) What do you plan to work on for this coming iteration (2 weeks)?
Weichong Zhao -x4x2b
1) What did you work on this past iteration (2 weeks)?
Set up MongoDB API with associates endpoint.
2) What were any major issues/challenges you ran into?
Setting up the route and paths.
3) What do you plan to work on for this coming iteration (2/3 weeks)?
Complete database setup for image storing and edit recommendations system with database
Ronin Cunningham - m0c2b
Scrum report for July 17