Task ID : 3.8
Description: Fill the Project Management section in the report
Goals: Complete Gantt Chart in Project Management section in the report
Success Criteria: Completion of the section by submission date (i.e. 25 Nov 2023)
Allocated Time: 30 Oct 2023 - 25 Nov 2023
Start Date: 30 Oct 2023
End Date: 25 Nov 2023
Owner: Jun Rui
Completed Gantt Chart for Project
Work has been committed
Work completion is in line with project deadline
No changes to the success or completion criteria of the task
30/10/2023 - 25/11/2023
Task ID : 3.8 Description: Fill the Project Management section in the report Goals: Complete Gantt Chart in Project Management section in the report Success Criteria: Completion of the section by submission date (i.e. 25 Nov 2023) Allocated Time: 30 Oct 2023 - 25 Nov 2023 Start Date: 30 Oct 2023 End Date: 25 Nov 2023 Owner: Jun Rui