Task ID : 3.8 Description: Fill the Project Management section in the report Goals: Complete Gantt Chart in Project Management section in the report Success Criteria: Completion of the section by submission date (i.e. 25 Nov 2023) Allocated Time: 30 Oct 2023 - 25 Nov 2023 Start Date: 30 Oct 2023 End Date: 25 Nov 2023 Owner: Jun Rui

Klovus commented 7 months ago

Completed Gantt Chart for Project Work has been committed Work completion is in line with project deadline No changes to the success or completion criteria of the task 30/10/2023 - 25/11/2023