LearnVocuabulary (LV) is a desktop application for people who prefer to use an offline version of the dictionary for learning purposes. More importantly, LV is optimized for those who prefer to work with a Command Line Interface (CLI) while still having the benefits of a Graphical User Interface (GUI).
[x] Issue labels set up e.g., type.*, priority.* (:heavy_check_mark: well done!)
[ ] Milestones created: v1.2 v1.3 [Please ensure milestones are setup until 'v1.4'] (:exclamation: try to do by next milestone)
[x] Some issues marked as type.Story e.g., link (:heavy_check_mark: well done!)
[x] Some issues prioritized using priority.* labels e.g., link (:heavy_check_mark: well done!)
Recommended progress for v1.3
Milestone v1.3 managed systematically
[x] A suitable deadline set (:heavy_check_mark: well done!)
[x] Issues allocated to it e.g., link (:heavy_check_mark: well done!)
[ ] A new jar file has been released on GitHub (:exclamation: try to do by next milestone)
Individual progress of @danielkoh94
Recommended progress for v1.3
[x] Has issues/PRs assigned for the milestone (:heavy_check_mark: well done!)
Individual progress of @alexehrs
Recommended progress for v1.3
[x] Has issues/PRs assigned for the milestone (:heavy_check_mark: well done!)
Individual progress of @harryqu123
Leftovers from v1.2
[ ] Merged updates to the Developer Guide (:exclamation: try to do by next milestone)
Recommended progress for v1.3
[x] Has issues/PRs assigned for the milestone (:heavy_check_mark: well done!)
Individual progress of @russellong95
Recommended progress for v1.3
[x] Has issues/PRs assigned for the milestone (:heavy_check_mark: well done!)
Tutor: @parvathy-sudhir-pillai
Note: the above observation was done by the CS2103-feedback-bot and covers changes up to 2018-10-25 00:00:00 only. If you think the above observation is incorrect, please let us know by replying in this thread. Please include links to relevant PRs/comments in your response.
Subject: feedback on week 10 project progress
See mid-v1.3 progress guide for more details of the activities mentioned below.
Team progress
Leftovers from v1.2
type.*
,priority.*
(:heavy_check_mark: well done!)type.Story
e.g., link (:heavy_check_mark: well done!)priority.*
labels e.g., link (:heavy_check_mark: well done!)Recommended progress for v1.3
Milestone v1.3 managed systematically
[ ] A new jar file has been released on GitHub (:exclamation: try to do by next milestone)
Individual progress of @danielkoh94
Recommended progress for v1.3
Individual progress of @alexehrs
Recommended progress for v1.3
Individual progress of @harryqu123
Leftovers from v1.2
Recommended progress for v1.3
Individual progress of @russellong95
Recommended progress for v1.3
Tutor: @parvathy-sudhir-pillai