start receiving on-going FBIRN phantom aquisitions #1

Open stowler opened 9 years ago

stowler commented 9 years ago

W, 20141203:

Emailed Michael after getting OK from Gopi:

Hi Michael,

How much trouble would it be for you to send the on-going FBIRN phantom acquisition to our dicom receiver (telomere)?

I don't want our group to take responsibility for analysis, but Lei and Gopi have had a hard time allocating resources for analysis & dissemination. If you start sending the acquisitions to us in addition to wherever else they're going, at least then our PIs would have the option of asking me to analyze the phantom data should they need it.

Thanks, Stephen

stowler commented 9 years ago

W, 20141210:

Per Michael: last FBIRN phantom acq was Nov 19th. Wed is their scheduled phantom time but has been getting bumped by paid scans.

Emailed Michael and Gopi:

Thanks for the update. Is there a way for us to get CSI to make reserved time for weekly QA so that it doesn't get bumped by other scans?

...per phone call w/ Gopi he says he'll ask Oshinski