Feature Request - Update Parent's Remaining Estimate #27

Open shaishandil opened 5 years ago

shaishandil commented 5 years ago

Hey, great extension - thank you for all the work you have put into this.

I do have a request that would make stand-ups and sprint planning much easier. Would it be possible to update the Remaining Estimate by the Time amount?

For example, if we set the Remaining Estimate to 13 on Monday. On Tuesday a developer logs 4.5 hours in the 'Times' tab. It would be great if the Remaining Estimate would be automatically updated to 8.5. If on Wednesday someone logs another 2 hours, the Remaining Estimate would be changed to 6.5.

Not everyone would want this feature, so maybe we'd have a setting to enable automatic update, or even have a checkbox in the 'Add Time' form:

image