Cables and connectors are ready. Ohmar, the electrical engineer from a vendor, and the team will be ready starting on the 11th of January 2023 for the electrical installation (following unpacking by LABMAN on the 9th of January). SJHA 5001. If @bernardusrendy is to do energized testing, remember to fill in Job Safety Plan and report to Ari or the Engineering Support Group.
Exhaust duct is installed. Need reducer and worm gear clamp from 4" to 3" which Yan has bought via Rosemary.
Compressed air and N2 gas lines are ready for compressed gas sources. @idocx is in charge of this and the system is ready.
Yan has reserved the B30 loading dock for LBCS parts.