Ultrafast High Temperature Sintering Phase 1
#77
Open
bernardusrendy
opened
3 months ago
bernardusrendy
commented
3 months ago
Purchase:
[x] Power supply 1500W 60V-25A, UL listed, LAN enabled (1 week lead time ARO, GEN 60-25-LAN)
[x] IR sensor (OPTCTL3MH3SF)
[x] Copper based AWG12 cables with high Tc, connectors, and how to solder
[x] Silicone (use the one in the lab probably) stopper or epoxies for cables to enable slight vacuum purging
[x] Slightly Thick Copper bars (will be drilled), screws, nuts, hand tapping, Tapping drill, spacer
[x] Welding mask
[x] AC Input cable for PSU
[x] Silver sheet or
[ ] Silver paste(check if we still have one in lab, should be enough)
[x] Quick and slow fuse 20A, 10A, 15A, DIN Rail fuse container
[x] Connectors for the cable in front of tube furnace
[x] Adhesive DIN rails (PSU is outside)
[x] Wrap the remaining quartz surface with aluminum foil to reflect infrared (protect eyes)
Check and Test:
[ ] Where to plugin the PSU, cable length
[ ] Test rubber stopper and purging
Finalize design:
[ ] All new installation hanging on tube furnace door
Purchase:
Check and Test:
Finalize design: