DMcC 12/02/24: Task1 Retrospective, Task2 Backlog Grooming:
51.5 Story Points attributed to Sprint3.
Main progress in areas of
So a lot of stuff done but incomplete. Tasks added to Sprint 4 where the gaps are small (e.g. #55 , #56 ) otherwise the user story has been returned to backlog.
Task3 - Sprint Planning & Issue Prioritisation Focus on: Redo deploy so that static and media files operate correctly #56 Add remaining custom functionality (reviews #57 and feedback form) Get additional addresses functionality working Apply consistent looks & feel (particularly to AllAuth forms) Consider additional/new PP5 elements (robots.txt, facebook page) #59
Task4 - UpdateReadme Not done - however I have gathered screenprints as each new feature is developed, tese are ready for adding into READme and should speed it up a little.
EPIC: #10
As a scrum master/developer I can follow Agile principles so that project functionality is achieved incrementally across sprints
Assumptions or Pre-Requisites:
Acceptance Criteria: (Must be completed before task is moved to 'Done')
Tasks