Task: Sprint 3 Retrospective, Sprint 4 Planning #54

Closed DeeMcCart closed 6 months ago

DeeMcCart commented 6 months ago

EPIC: #10

As a scrum master/developer I can follow Agile principles so that project functionality is achieved incrementally across sprints

Assumptions or Pre-Requisites:

Acceptance Criteria: (Must be completed before task is moved to 'Done')

Tasks

DeeMcCart commented 6 months ago

DMcC 12/02/24: Task1 Retrospective, Task2 Backlog Grooming:

51.5 Story Points attributed to Sprint3.
Main progress in areas of

So a lot of stuff done but incomplete. Tasks added to Sprint 4 where the gaps are small (e.g. #55 , #56 ) otherwise the user story has been returned to backlog.

Image

DeeMcCart commented 6 months ago

Task3 - Sprint Planning & Issue Prioritisation Focus on: Redo deploy so that static and media files operate correctly #56 Add remaining custom functionality (reviews #57 and feedback form) Get additional addresses functionality working Apply consistent looks & feel (particularly to AllAuth forms) Consider additional/new PP5 elements (robots.txt, facebook page) #59

60

Task4 - UpdateReadme Not done - however I have gathered screenprints as each new feature is developed, tese are ready for adding into READme and should speed it up a little.