Extended Sprint 5 to revised project submission date- so Sprint 5 was 13 days long instead of the normal 7 days. The burndown chart showing time spent by EPIC reflects this:
Considerable time was spent in Sprint5 on code refactoring, testing and adjustment. At time of submission there are still open issues. This project would benefit from additional work to quickly progress to a Version 1.1 to include bug fixes. The issue log is shared in the comment below, and a screenprint of open issues remaining is shown
ISSUE LOG is at https://docs.google.com/spreadsheets/d/1c03-8MvHUGg_ebzb8hMKn2PpbqHV23T5cvY5oasyAaE/edit?usp=sharing
Analysis of isssues at time of PP5 submission: issues raised : 137** issues closed: 97 future : 26 workaroud: 6
8 issues remaining (bugs)