Open DeeMcCart opened 11 months ago
Derek came over Friday 11/10/23 and he hung doors with my help Sean 28/10/23 corrected the double doors so they now close (planed close to 3/4 inch off left hand frame from kitchen side) Visually they look right. 2 doors from hall to kitchen and sitting room checked for alignment and door stops and archictraves mostly installed (not hall -> kitvhen as need to see how this will work with cloakroom door),
Door sourced for downstairs cloakroom 19/12/23 Door installed Thurs 21/12/23 as part of cloakroom tiling etc
EPIC: DOORS
As a role I can capability so that received benefit Assumptions:
Acceptance Criteria
Tasks
[x] Re-hang hall-> kitchen door, hall -> sittingrom door, and sittingroom -> kitchen double doors
[x] Handle for hall-> kitchen door
[ ] Receiver for hall-> kitchen door
[x] Architrave for interior (kitchen side) hall-> kitchen door
[x] Re-hang hall-> sittingroom door
[x] Handle for hall-> sittingroom door
[x] Receiver for hall-> sittingroom
[x] Architrave for exterior (hall side) hall-> sittingroom door
[x] Architrave for interior (sittingroom side) hall-> sittingroom door
[x] Re-hang sittingroom door -> kitchen double doors
[x] Plane doors to close in middle
[x] Plane doors to close in middle
[ ] Architrave for exterior (sittingroom side ) sittingroom -> kitchen doors
[ ] Architrave for interior (kitchen side) sittingroom -> kitchen doors
[x] Source door for downstairs cloakroom
[x] Hang hall-> cloakroom door issue #53
[x] Handle for hall-> cloakroom door issue #53
[x] Receiver for hall-> cloakroom issue #53
[ ] Architrave for exterior (hall side) hall-> cloakroom
[ ] Complete interior plasterboarding & architrave cloakroom
UPSTAIRS DOORs - separate task