(FY23 Q1) - Run NREL-5MW in ABL with FSI+Controller #6

Open psakievich opened 9 months ago

pscrozi commented 9 months ago

Solvers diverged on Frontier. Ashesh is having problems on Eagle's infrastructure. System level debugging to do there.

pscrozi commented 9 months ago

Ashesh had it running, but Eagle went down 8 hours early. Was 9 - 10 rotations in, and seems to be working. We don't understand fully the behavior of the controller, but still early in the run.

pscrozi commented 9 months ago

We're in a holding pattern until Eagle comes back.

Phil put together a fresh build with the driver on Attaway. We can do runs at Sandia with this build.

pscrozi commented 9 months ago

Phil copied the pre-cursor from Frontier over to Sandia machines. Can start running this today. May need to update Neil's to use the same pre-cursor as well on SNL machines.

pscrozi commented 9 months ago

Ashesh said he would relaunch these yesterday. Looks like he's been running for 1.5 hours already as of 8:45 a.m. on 10/6.

pscrozi commented 9 months ago

Ashesh has run 18 rotations so far, as of 10/9. Can start writing up report on this now for FY23 Q1. Tower, ABL, etc.

Need to start post-processing the data. 18 rotations is already enough.

Mike will add skeleton for report on Sharepoint on 10/9 and point us to it.

psakievich commented 9 months ago

I was able to run this on Attaway over the weekend as well with my build. It ran for 1 revolution in 17.5 hours with 16 nodes. This was a test to verify that the issues with the IEA-15MW turbine were model related and not to do with my latest build on Attaway.

pscrozi commented 9 months ago

Have Ganesh and Ashesh reviewed the loads? Not in detail yet.

Ashesh has some nice plots already made. Phil will work with Ashesh to add more information to the plot, especially to explain the abrupt drop at ~18 s when FSI takes over. We should annotate this: where FSI starts, where it is fully transitioned, etc.

Mike asked Ganesh for a wish list of figures for the report. Need to merge all software components with main.

pscrozi commented 9 months ago

Mike is working the slide deck with Ashesh. It is pretty much done.