When new issues are created, we need to add them to the project (via the sidebar).
At first, they will have no status
Once we agree that this is something we want to work on, we'll assign the "To-do" status
When someone wants to work on an issue, we assign it to them
Once they start working on it, we can change the status to "In progress"
Once complete, we can change it to "Done"
The project also has a milestone view, grouping the same issue not by status, but by milestone. That is a nice alternative for us to rally around specific milestones.
@chrislueders and @editwentyone, what do you think? Does this setup work for you?
I set it up right here.
When new issues are created, we need to add them to the project (via the sidebar).
The project also has a milestone view, grouping the same issue not by status, but by milestone. That is a nice alternative for us to rally around specific milestones.
@chrislueders and @editwentyone, what do you think? Does this setup work for you?