Closed tes36 closed 11 months ago
Are you saying that the event changes from a timed event to an all-day event in Google Calendar when you edit something else in the event using Sheets2GCal, even though you didn't remove the Start/End times?
exactly that, on Sheets2GCal sheet it still appears START and END time but if I go to the calendar, it appears checked as an ALL-DAY event
If you only edit the Start and/or End times and update Google calendar from the Sheet does that work correctly? It sounds as though Sheets2GCal can't read the Start or End times when updating the event - are you sure that the Column header names haven't been changed?
They haven't been changed
Thanks, I'll be testing this and your other issue this evening and will post back as soon as I have news.
I can't reproduce this problem - what are your settings for the Sheet's "locale" (in the Sheet Settings > General > Locale)? Also what is the Hour/Minute separator (usually a colon e.g 13:20) and when you double-click a "Start Time" does the separator change?
Regional configuration is set to Spain, I've tried 13:20 and also 13:20:00
I can't reproduce it now. Also weekly events that were transformed to ALL DAY are actually set to TIMED events, so it's properly working.
Ok, I have no idea how that could have caused that but please let me know if it happens again!
When I create a new event with the “start time” and “end time” cells having values, the event is created with a start time and end time, it works fine.
If after that, I update the event, it becomes an all-day event.
But in the cells, it shows the start and end time, it is displayed as an all-day event in the calendar (with the all-day event checkbox set to true).