Open JessicaMarine1 opened 1 year ago
Per Sarah Bryant: as soon as the vendor is done with the Drupal 9 upgrade, they will be shifting immediately to the Drupal 10 upgrade. The earliest expected date of completion is late September 2023.
3/16/23: Discussed status of Drupal upgrade with SD team. Decision: continue to maintain the status quo (launching a few pieces a week) for now. Pivot if/when we need to. If the development asks become too much, we’ll have to be frank with PBS about what our team can do.
9/21/23: Eleni informed SD team that OSC was going to try to migrate the workplace site into Drupal. 10/3/23: Corey in OSC is working on a test (2 pages) to see how easy/hard this will be.
Change log for Corey (OSC)
1/2/2024 Update: The workplace website is almost ready to transition into GSA.gov :tada: Corey from OSC has done a phenomenal job at converting the site into GSA’s CMS (https://preview.gsa.gov/sandbox/corey-ks-sandbox/workplace) !!
Next steps
Tasks