Greg-Tan / pe

0 stars 0 forks source link

Hard to test schedule page for future scheduling #9

Open Greg-Tan opened 5 months ago

Greg-Tan commented 5 months ago

it is unclear in the UG when the calendar is supposed to start and end at which can be confusing to the user because it becomes hard to schedule for dates past the current dates displayed. As a tester I also am not sure if im supposed to schedule beyond the current set of dates

soc-pe-bot commented 5 months ago

Team's Response

image.png

The limitations are clearly stated in the UG as per point 1.

Items for the Tester to Verify

:question: Issue response

Team chose [response.Rejected]

Reason for disagreement: [replace this with your explanation]