When performing optimization per week, and using the resolution by week, we would assume that chronix2grid solves only one optimization problem.
However, if your data does not start a monday (or a sunday, i did not checked) then chronix2grid will split the resolution in 2 partial weeks (and you will get trouble "at the junction")
When performing optimization per week, and using the resolution by week, we would assume that chronix2grid solves only one optimization problem.
However, if your data does not start a monday (or a sunday, i did not checked) then chronix2grid will split the resolution in 2 partial weeks (and you will get trouble "at the junction")