Weekly Update

What has been done?

Met with Billy and team to discuss questions around how to get from 0-1 and what features will bring the most value

Status Planning

Risk Curtis still needs to assign a data engineer to this task with the appropriate skillset.

Deliverable Date TBD

What will be done?

coilysiren commented 8 months ago

I'm going to try to scope some discovery work where I deploy AWS Redshift and AWS Quicksight

coilysiren commented 8 months ago

https://github.com/HHS/simpler-grants-gov/issues/1411 https://github.com/HHS/simpler-grants-gov/issues/1410

EOKENAVA commented 8 months ago

Weekly Update

What has been done?

Status On Track

Risk

Deliverable Date April 30th

What will be done?

sarahknoppA6 commented 8 months ago

@EOKENAVA is there any update about the Nava review of the deliverable spec? Last update & discussion earlier this week indicated feedback from Nava would be coming, but we need to know when.

acouch commented 8 months ago

We have a suggestion to move the work to two 30ks that has a high-level endorsement. The April delivery date is still on track. We need to circle back with @widal001, hopefully next week to hammer out the task details. From there we can update the date if necessary.

EOKENAVA commented 8 months ago

Weekly Update

What has been done?

Status On Track

Risk

Deliverable Date April 30th

What will be done?

sarahknoppA6 commented 8 months ago

@widal001 see previous comment a couple of comments up- did the team follow up with you on this?

sarahknoppA6 commented 8 months ago

@EOKENAVA @margaretspring please phrase the risk as an if/then statement. Also, I believe we'd like to discuss today at ToT if there is anything that can be done/started on the delivery dashboard in the absence of the data engineer. cc @lucasmbrown-usds

acouch commented 8 months ago

We will have a decision for the dashboard and storage by the end of the sprint.

We will still need to go through the process of creating and estimating the 10Ks and getting approval.

margaretspring commented 8 months ago

Weekly Update

What has been done?

Status On Track

Risk

Deliverable Date April 30th

What will be done?

margaretspring commented 8 months ago

Weekly Update 4/3

What has been done?

Status Planning/implementation

Risk

Deliverable Date Currently slated for April 30

What will be done?

margaretspring commented 7 months ago

Weekly Update 4/11

What has been done?

Status Planning/implementation

Risk

Deliverable Date Currently slated for April 30

What will be done?

widal001 commented 7 months ago

Updated the ticket format to reduce discrepancies with the deliverable spec.

margaretspring commented 7 months ago

Weekly Update 4/17

Milestones: [10k]: Delivery dashboard - Planning (100% done) | [10k]: Delivery dashboard - ETL (10% done) | [10k] Delivery dashboard - Infrastructure (50% done) | Delivery dashboard - Enhancements and fast follow (0%)

What has been done?

Status In Progress

Risk SIA approval for Metabase

Deliverable Date TBD

What will be done?

margaretspring commented 7 months ago

Weekly Update 4/24

What has been done?

Status In Progress

Risk

Deliverable Date Sprint 25 - Jun 11

What will be done?

lucasmbrown-usds commented 7 months ago

What does "If further BI tool questions come up" mean? Do you just mean questions about whether the tools work for our security requirements etc? Something like, "If during implementation, we learn things (such as how the selected tool can or can't meet security requirements) that make us need to switch our planned approach to the BI tool, then it could take longer to complete this than expected"?

acouch commented 7 months ago

This was referring to the security questions.

margaretspring commented 6 months ago

Weekly Update 5/1

What has been done?

Status In Progress

Risk

Deliverable Date Sprint 25 - Jun 11

What will be done?

acouch commented 6 months ago

Weekly Update 5/8

What has been done?

Status

Risk

Deliverable Date Sprint 25 - Jun 11

What will be done?

widal001 commented 1 month ago