  1. Task title ID: #103
  2. What is the task about? Amend the changes to the current class diagram based on the professor's feedback
  3. What are the goals of the task? Make all the necessary changes to the current class diagram
  4. Success or completion criteria. Ensure that all changes to the class diagram meets the requirement set by the prof
  5. Allocated time: 6 days
  6. Start date and end date of the issue/task. Start: 24/10/23 , End: 28/10/23
  7. Who is the owner? Taufiq
  8. The status of the task. High
  9. What is the Priority of the task? In Progress
whoistfq commented 11 months ago
  1. Describe the work done in detail: Parameters were added to the control class and the relationship between classes were amended as well.
  2. Has this work been committed to the repo? Yes
  3. How does the work affect the completion deadline? It does not affect the completion deadline
  4. Are there any changes to the success or completion criteria of the task?No
  5. Start date and end date of the work done for this comment. Start: 23/10/23 , End: 25/10/23