INF2001 / TEAM-PROJECT-P11-3

0 stars 0 forks source link

3.4 Software Testing #106

Closed farhanhan1 closed 10 months ago

farhanhan1 commented 11 months ago
  1. Task title ID: #106
  2. What is the task about? The task involves comprehensive software testing of the current development module. This includes a mix of Black Box and White Box Testing to ensure code integrity, functionality, and user experience.
  3. What are the goals of the task? To identify and address any bugs or issues, validate the software against requirements, and ensure robust performance and user experience and expected results are met.
  4. Success or completion criteria: When all identified bugs are resolved, the software meets all functional and performance requirements and passes all testing procedures.
  5. Allocated time: 3 days
  6. Start date and end date of the issue/task Start: 8/11/2023 End: 11/11/2023
  7. Who is the owner? Farhan, Gabriel and Clement
  8. The status of the task: In Progress
  9. What is the Priority of the task? High
farhanhan1 commented 11 months ago
  1. Describe the work done in detail: All project tasks and milestones were identified and added to the Gantt chart. These tasks were also allocated to different team members to ensure equal workload.
  2. Has this work been committed to the repo? Yes
  3. How does the work affect the completion deadline? It would not change the project completion dateline.
  4. Are there any changes to the success or completion criteria of the task? No, there was no changes to the completion criteria of the task.
  5. Start date and end date of the work done for this comment. Start: 8/11/2023 End: 14/11/2023