Closed yichingt closed 1 year ago
Task Completed Has work been committed to repo?: Yes How work affected the completion deadline?: Task was not late and the deliverables were submitted before the deadline. Any changes to the success or completion criteria?: No changes were made Start Date - End Date: 1 Sep - 22 Sep Additional Comment: This task was closed late as it was inadvertently overlooked
Task ID 1.5 Description: Writing of report for M1 as per the template and requirements Goals: Completion of M1 report with required sections Success or Completion Criteria: Completion of M1 Report for deliverables Allocated Time: 19 Days Start - End Date: 1 Sep - 22 Sep Owner: Work is allocated between the members Priority: High