Closed yichingt closed 1 year ago
Completion: Yes Work committed to Repo?: Yes How work affect the completion deadline: The work being completed late will affect task 2.4.1.3, but effectively, this and the latter tasks are worked in parallel with each other Are there any changes to the success or completion criteria?: No change Start Date and End Date: 1 Oct - 10 Oct Additional Comment: This task was closed late as it was inadvertently overlooked
Task ID 2.4.1.2 Description: Working with the sequence and class diagram, and the front-end to sort what and how the information will be withheld and stored within the database. Goals: Completion of diagram and confirmation on the other two diagrams Success or Completion Criteria: Completion of the diagram Allocated Time: 4 days Start - End Date: 1 Oct - 4 Oct Priority: Medium