euterpe87 commented 1 year ago

Hi everybody, I'm trying to run the model with the below time settings (namely with 1 year time steps), but I get errors related to interpolation issues (e.g. "Skipping interpolation for BC in year 2021 due to mismatch.") or input data issues. Is it actually possible to run the model with 1 year time steps? If yes, does it require customization? I haven't changed anything from the default settings other than the below time settings, and I'm running the reference scenario. Thanks so much for any help!

`<?xml version="1.0" encoding="UTF-8"?>

1975 2015 2100 1705 2005

`

euterpe87 commented 1 year ago

wrong channel