Plan and meet with control one (and or Abatement Center) to make them aware that the site will be down from evening of September 15 to September 16.
Ensure that they have paper process established to look up SR from 311 site, dispatch accordingly, and update the SR's and corresponding WO's once the site is back up again.
Plan and meet with control one (and or Abatement Center) to make them aware that the site will be down from evening of September 15 to September 16. Ensure that they have paper process established to look up SR from 311 site, dispatch accordingly, and update the SR's and corresponding WO's once the site is back up again.