1.7.2 Create a Project Management Plan #7

Closed KotoneZQ closed 1 year ago

KotoneZQ commented 1 year ago

Follow the template in the slides (read ahead week 3 lecture materials).

Task title ID: M1.4.2 Project Management #7 What is the task about?

Create a Gantt chart with the provided details for our project schedule

What are the goals of the task?

To provide a schedule of what we have planned to do in estimation as well as keeping track of each member's tasks To assign each task to members with indicated start and due date

Success or completion criteria.

Finish the Gantt chart with a detailed and estimated schedule

Allocated time

2 Days

Start date and end date of the issue/task

19 Sept - 21 Sept

What is the priority of the task

High priority

Kai-i-i-i commented 1 year ago

reviewed

KotoneZQ commented 1 year ago

Created a Gantt chart in Google Drive Fill in the required tasks and summary for each Milestone of the project Indicate task owner, start date and end date, and percentage of task complete for currently and completed tasks

KotoneZQ commented 1 year ago

17 Sept 2023, 8pm - 12am

Discussed Gantt chart among group Modified and fill up the remaining tasks for each Milestone of the project

KotoneZQ commented 1 year ago

Pending reviewed from team members

Jr-Goh commented 1 year ago

reviewed

brandonbljl commented 1 year ago

reviewed

Kai-i-i-i commented 1 year ago

reviewed

gitdanzel commented 1 year ago

reviewed

KotoneZQ commented 1 year ago

reviewed

KotoneZQ commented 1 year ago

closed (22/9)