Leeyp / pe

0 stars 0 forks source link

Sequence Diagram (Figure 2: Initialization) Bug #8

Open Leeyp opened 3 years ago

Leeyp commented 3 years ago

As we have learned in class, activation bar of a Sequence Diagram should start when the object is constructed.

image.png

This sequence diagram is floating in mid-air. Very strange. But for the rest, they are correct.

nus-pe-bot commented 3 years ago

Team's Response

This is an issue with PUML image generation.

Items for the Tester to Verify

:question: Issue response

Team chose [response.Rejected]

Reason for disagreement: Tutor verification required, as other activation bars (such as Ui, Storage) in the screenshot were not affected.