Error calculating earned value #1233

Closed kwoot closed 6 years ago

kwoot commented 13 years ago

(Original Bugzilla Bug ID: 1089)

Date: 2011-06-06 18:54:12 From: Javier Morán \<jmoran@igalia.com> To: Susana \<smpedreira@gmail.com> Version: libreplan-1.2 (1.2.x) Last updated: 2013-07-18 10:36:29


(Note: this issue was migrated automatically with bugzilla2github.py tool )

kwoot commented 6 years ago

Bugzilla Comment ID: 2844 Date: 2011-06-06 18:54:12 From: Javier Morán \<jmoran@igalia.com>

With the attached dump there is a bad calculation of the earned value, especifically, for the BCWS for the project "Proyecto de prueba".

It is put the value now bellow the hours planned but in another point of the time axis ¿?.

Probably the error could be in navalplan-1.1 but not sure.

kwoot commented 6 years ago

Bugzilla Comment ID: 2845 Date: 2011-06-06 18:54:49 From: Javier Morán \<jmoran@igalia.com>


Attached file: dump.sql File description: dtabase dump

kwoot commented 6 years ago

Bugzilla Comment ID: 4528 Date: 2013-07-18 10:36:29 From: Elena \<elena.dasseni@coster.eu>

I am using LibrePlan, and still the problem exists. According to the Details view, my project has a BAC of 7264 hours, but when it comes to the Earned Value tab, it says 6526.

kwoot commented 6 years ago

Has been fixed by changing calculation to higher resolution.