ManiacalLabs / Engravinator.com

Creative Commons Attribution Share Alike 4.0 International
1 stars 4 forks source link

Build Guide: Running Cables #25

Closed haooken closed 5 years ago

haooken commented 5 years ago

Install Limit Switches: Mention in that note that "we will be covering the installation of 1 limit switch per axis in this guide". This removes ambiguity regarding the need for following the remaining steps in this section.

"---- take pics of soldering process ----" - Need pics for this?

Run the Y-Axis Limit Switch Cable: "...then press the ??mm slot cover into the channel." - Need measurement for this slot cover.

Mount Laser/Servo and Run Cable: Star at end of Note 1, does this indicate a footnote? Should be removed?