Task title ID: (Task ID #6)

What is this task about? Describe in detail Write all our project content into M1 report

What are the goals of the task? Describe in detail To ensure all the administrative, requirements gathering, use cases and workflow are in the report

Success or completion criteria. Describe in detail The report has to be in the correct format and non section is missing or incorrect

Allocated time 3 weeks, 4 days

Start and end date for the issue/task Start date: 5th September 2023 (Tuesday) End date: 23rd September 2023 (Saturday)

Who is the owner? Owner is the person in charge of the task and should be created and maintained by the owner. Owner: All

Task Status. Usually under "To-Do". To-Do

What is the priority of this task? Low

LilZBJ commented 1 year ago
  1. Describe the work done in detail Team report for part Milestone 1 (M1) updated and completed. Relevant sections have been filled with information and images, along with necessary explanations.

  2. Has this work been committed to the repo? Work has not been committed to the repository, as it is a google document.

  3. How does the work affect success of completion criteria? The work done finishes the report, which will be submitted in PDF format, and is a critical component of part M1.

  4. Start and end date of the work done From 29th August (Tuesday) to 23 September (Saturday)