The Project Formulation to Implementation DG signifies the transition of the solution project from the Formulation Phase to the Implementation Phase, and occurs whenever the solution project is on contract/agreement with the SNWG MO, has completed any other needed agreements, and is ready to start implementing or has completed a prototype of the solution. The Project Formulation to Implementation DG takes the form of a meeting where the Project Plan is revisited.

Before the meeting:

During the meeting:

After the meeting:

Table 6: Project Formulation to Implementation Expected Inputs and Outputs (Table 6 in Program Plan, Section 12.2.2.3) image