Motivation: HLS-VI was selected as a cycle 3 solution to the SNWG survey due to its ability to meet many agency’s needs for easier access to high-fidelity vegetation information.
Description: Test the SNWG cycle 3 Vegetation Indices suite.
Acceptance/Completion Criteria:
[x] Perform large scale integration testing with VI data
[ ] Test end-to-end capability to send data to LPDAAC in UAT environment
[ ] Implement a reconciliation process for staged HLS-VI data with LPDAAC in UAT
Risks, Dependencies & Blockers:
Dependency:
Coordination with LPDAAC and SNWG
Risk:
There can be request for additional requirements or changes from LPDAAC or SNWG
Mitigation: Plan regular status meetings and provide status updates
Motivation: HLS-VI was selected as a cycle 3 solution to the SNWG survey due to its ability to meet many agency’s needs for easier access to high-fidelity vegetation information.
Description: Test the SNWG cycle 3 Vegetation Indices suite.
Acceptance/Completion Criteria:
Risks, Dependencies & Blockers:
Blocker: N/A