NASA-IMPACT / snwg-implementation

Tasks for the SNWG Management Office (MO)
1 stars 0 forks source link

Progress Air Quality #101

Closed CherrelleTucker closed 4 months ago

CherrelleTucker commented 5 months ago

Summary

Complete Air Quality/Pandora Milestones

Acceptance Criteria:

- [ ] Finalize and sign the Pandora Sensors Project Plan
- [x] Hold Formulation to Implementation Decision Gate for PM2.5 and GMAO 
  - [X] GMAO Forecasts: May 1, 2024 
  - [X] PM2.5 Forecasts: April 25, 2024 

Dependencies

Signature from the Pandora Sensors project lead The Project Plan was modified slightly to account for expanded Stakeholder Engagement considerations. Section needs review and approval by multiple parties.

Risks

None currently identified

Future PI

Finalize and sign the GMAO and PM2.5 Project Plans

CherrelleTucker commented 5 months ago

2024-05-01 GMAO F2I Decision Gate

2024-04-25 SNWG - PM2.5 F2I Decision Gate