Objective 3: Progress c3 solutions - TEMPO NRT #139

Open CherrelleTucker opened 1 week ago

CherrelleTucker commented 1 week ago

Summary

Acceptance Criteria:

- [ ] Formulation to Implementation Decision Gate
- [x] DAAC Assignment
- [ ] Project Plan signing

Dependencies

C3 TEMPO NRT: DAAC Assignment and ICD dependent on ESDIS

Risks

Future PI

Stretch goal: ICD, if needed

CherrelleTucker commented 4 days ago

From: Grullon-Pingon, Rita A. (GSFC-4230) [rita.a.grullon-pingon@nasa.gov](mailto:rita.a.grullon-pingon@nasa.gov) Sent: Tuesday, October 22, 2024 4:04 PM To: Gregory, Sean P. (MSFC-ST14) [sean.p.gregory@nasa.gov](mailto:sean.p.gregory@nasa.gov) Cc: Smith, Russell W. (GSFC-5850) [russell.w.smith-2@nasa.gov](mailto:russell.w.smith-2@nasa.gov) Subject: PBL POC

PBL POC: Russell Smith (GES DISC DAAC Engineer) - cc in this email. Russell should be invited to the ATP gate review.

TEMPO NRT DAAC Selection Status: DAAC has been assigned 10/3/2024.

Rita.


Rita Grullon-Pingon NASA Earth Science Data Information System (ESDIS) Deputy Project Manager Science Operations

Phone: 301-614-5372 (work) 301-337-1653 (cell)
Email: rita.a.grullon-pingon@nasa.gov NASA Goddard Space Flight Center Greenbelt, MD 20771