"Update from the meeting today:
Newsletter is in progress (hope to send it out by the end of this week pending Katrina's approval).
LP.DAAC has committed to developing training, but we're not sure if DAAC selection has been confirmed (may want to check with Jeanne')
Pontus has reached out to Melanie Cook from ARSET several times with no response. He plans to ping her again."
Pontus 9:54 AM Sorry for the delay -- yes, I am working with ARSET to design stakeholder engagement activities related to the HLS VI solution. We haven't formalized the collaboration yet but we agreed to work together. The stakeholder engagement will include how to work with the data on the LPDAAC
Cherrelle Tucker :office: 10:00 AM Thanks! Do you think formalizing that collab will be done in this PI (next 4 weeks) or take a bit longer?
Pontus 10:15 AM Should be done in the next four weeks
Description
Continue HLS-VI Stakeholder Engagement support
Acceptance Criteria:
Dependencies
Risks