Closed CherrelleTucker closed 5 months ago
HLS-VI ORR tentatively scheduled April 1. - confirmed with Madhu
I can have that [section of the HLS-VI project plan] ready by the end of the week - Madhu; 2024-03-19
Cherrelle Jeanne' thinks we should probably push the ORR back. Do you have the estimated time frame when the product will go fully live at the DAAC?
Madhu 3:35 PM I'd say we'll probably be ready mid April or so, but to be safe I'm inclined to push it to May 1.
2024-03-20 Financial: trying to get in touch with Karen Michael, no response yet.
Milestone
M4 Cycle 3
Quarter
Q2 (1 Jan to 31 Mar)
Description
Obj 4.D Summary: Progress HLS-VI Owner: Sean Gregory
Examples and Resources
No response
Deliverable
Implementation Blockers or Dependencies
Dependencies: Open questions about appropriate handoff plan will require input from HQ Risks None currently identified Future PI: Hold Operational Readiness Review (ORR)
Related Issues
No response