2024-01-31: Meet with Tom Hanisco at AMS - Ask about walls preventing sensor installments, how we can help move things forward
2024-02-09: Draft gap analysis reports - Anita to start consolidating "need, requirements, and gaps" reports.
2024-02-15: EPA user story for SNWG-MO - Reach out to EPA contacts and ask for specific information on how TEMPO will help them or aid in specific decisions.
Make a quick slide describing the story =)
2024-02-23: (TEMPO) Discuss Training Needs with Aaron
Milestone
M6 Stakeholder Engagement Program (SEP)
Quarter
Q2 (1 Jan to 31 Mar)
Description
Objective 6.A Summary: Execute Phase 2 of the SNWG-SPoRT 3 Solution Engagement Plan
Owner: Pontus Olofsson, Anita LeRoy, Cherrelle Tucker
Examples and Resources
No response
Deliverable
Implementation Blockers or Dependencies
Dependencies: Participation of solution project teams Risks None currently identified Future PI:
Related Issues
No response