Closed jordanpadams closed 2 years ago
:clock1: Deferring to B12.1 due to deployment procedures that didn't quite work for the team. Not required for B12.0 build / deployment.
📆 October status: On schedule
@nutjob4life once we wrap up the CI work, I will need some help updating how this docker image is built and deployed to be open source
📆 November status: Initial work completed, but task has returned to TODO. Re-assigned to new developer. On schedule to meet expected date.
All sub-tasks completed
:calendar: march status: delayed to to lack of available resources and deferred to B12.0