Closed jordanpadams closed 8 months ago
📆 January status: Overall SBN-PSI architecture completed. Nucleus pilot start delayed 1 sprint. No impact on delivery
📆 February status: Per decisions made regarding SBN-PSI architecture, we will leave their pipeline on-prem, and deploy a baseline PDS Nucleus pipeline for B13.1. Any other deployments will occur next build. Start delayed, but no impact on build.
📆 June status: Initial PoC being worked to load some MDIS data into the Registry using Nucleus. CSS will be next. On schedule.
📆 July status: Deferred to B14.1 per delays from ISA documentation requested by stakeholders, and the delay has been discussed and agree upon. New roadmap has been accepted.
📆 October status: Tightly coupled with #66 , work for improving baseline nucleus is ongoing. Demo completed on 10/27. Preparing for beta production execution in November. On schedule
📆 November status: Delayed until December awaiting ISA approval between discipline node and EN to begin pushing data.
📆 December status: CSS has yet to deliver data to the cloud. Task delayed into February. No impact on delivery.
📆 01/2024 status: In work. On schedule.
📆 02/2024 status: A baseline deployment has bene completed in development. Will have follow-on task in B15.0 to deploy in Test and Production