Open viviant100 opened 1 year ago
📆 December status: Delayed start by 1 sprint. No impact on delivery.
📆 01/2024 status: Deferral anticipated. Meeting with SBN on 02/06 to discuss. No impact on other tasks.
📆 02/2024 status: Deferring. Not a top priority for stakeholders for B14.1. Will work with SBN in B15.0 once we have CSS data in production.
📆 05/2024 status: Delayed until later in the sprint due to significant delays in MCP onboarding. This is a consolidation/cost cutting activity that is not required for nominal operations. No impact on system.
📆 07/2024 status: Deferred until B15.1. The data this relies on (Catalina Sky Survey) will not be switching over to production in the cloud until FY25. Will add this to plans in early B15.1. No impact on other nodes or build since this is something we work alongside data migration activities.